Strict adherence to all Clough and BHP safety requirements – proactive engagement with on-site teams.
Remote site logistics and workforce roster with the flexibility for reactive short notice mobilisations.
Compliance with all BHP design, technical and performance criteria.
Pre-construction deliverable dates met against the ongoing facility design process.
Flexible work team mobilisations to meet aggressive and evolving work schedules.
Compliance with all turnover (ITRs), finalisation procedures (Commissioning Reports) and handover documentation (MDR, IOM and Training Procedure).
Turnkey delivery of 24/7 operational facility Outside Air system via external processing unit and upstream Dust Extraction unit with Ablutions, Crib and Storage area exhaust systems.
Zero Lost Time Injuries or Near Misses for the project duration.
Extensive workshops with the client and end-user to ensure services were fit for purpose and relevant to the facility’s daily needs.
Maximised offsite opportunities – over 50% of the installation to demountable facility buildings and equipment FAT.
Project peak labour – 8 workers.
Approval of the modular structural support system for ductwork and plant was the first design used on a BHP mine, negating the need for painting, welding, and NDT.
Provide all Mechanical Electrical services and integrated control system via Mechanical Services Switchboard.
Complete all commissioning works, integration testing and emergency shutdown procedures.