Port Hedland Boulevard – Central Plant





AboutThe Client



Description



Project Details

  • Location: Port Hedland, WA
  • Construction Value: $ 1.5M
  • Client: Fortuna
  • Consultant: Tailored Engineering
Image courtsey of Fortuna
Image courtsey of Fortuna
Image courtsey of Fortuna
Image courtsey of Fortuna

Delivery

Overall management and delivery of all works.

  • All key program milestone dates achieved.
  • Zero unplanned service interruptions.
  • Zero LTIs or Near Misses.

Comprehensive methodologies developed for each phase of project;

  • Existing plant decommissioning.
  • Crane operations and forklift operations
  • New plant installation and connection with no extended client service interruption
  • New plant and service integration into existing systems.

Provide all upgrades to Mechanical Electrical services and the Building Management System.

Replacement of all Woolworths shop front fabric duct systems with specialist cleaning of all metal ductwork.

Completion of all plant and service commissioning and integration with in-house Commissioning Department.

Comprehensive training and handover procedure with client facility engineering team training.