Replacement of air conditioning and chilled water plant, including air-cooled chiller and air handling unit serving the level 7 Concentrator building. The supply and installation of new ductwork throughout the laboratory.
Zero Lost Time Injuries or Near Misses for the project duration.
Offsite modular construction and performance testing.
Management and coordination of all works and trades.
Provision of temporary air conditioning.
Demolition of all existing redundant services.
Provide all Mechanical Electrical services and Building Management System.
Complete all commissioning works and integration testing
Conformance to all Rio Tinto working procedures and permits for a live mine site environment.
Compliance with all Rio Tinto and mine specific design, technical and performance criteria.
Detailed work methodologies were generated for all project phases through close collaboration with the client’s team to ensure no impact on day-to-day operations.
Compliance with all turnover, finalisation procedures and handover documentation.
All works were completed safely and on schedule to the expected quality requirements.